The Jinzhong 1000kV Substation Main Transformer Expansion Project

Winning bid products: BKDGKL-80000/110, CKDGKL-9600-110-12


Winning bid converter station: Jinzhong 1000kV Substation


Operation year: November 2021


The Jinzhong 1000kV substation main transformer expansion project includes the expansion of one set of main transformers, installation of one set of low-voltage shunt reactors, one set of low-voltage shunt capacitors, and one station transformer. Currently, the overall progress of the "four connections and one being leveled" has reached 40%, and the civil engineering has been completed by 24%. It has been put into operation by the end of November 2021.